Tanker 4 Construction - Week 5
 
By Assistant Fire Chief Eddie Raley
September 11, 2011
 

This week, after the new Tanker 4 finished on the main assembly line, it went through alignment and initial pump testing. It is now on the line where it is reviewed after testin. This is also where additional detail work can be completed, and reflective striping is applied (when so ordered). Next week, the road test should be completed and Tanker 4 should be in third-party pump testing.

A few RVFD members will be traveling to Pierce Manufacturing Inc. September 22-23rd for final inspection.

 
Units: New Tanker 4